PUBLIC EVIDENCE
Read the source documents.
Primary records first. Reporting is used to establish what has been publicly reported, not to replace the underlying documents.
Project Silo Concept Plan · June 27, 2025
Primary project record · concept / design may change
Open PDFPrimary project record · concept / design may change
Brighton PAC Comment Letter · July 31, 2025
Primary review comments · traffic, water, sewer, drainage and process questions
Open PDFPrimary review comments · traffic, water, sewer, drainage and process questions
Silo / Willard Property Pre-Application · July 23, 2025
Primary pre-application record
Open PDFPrimary pre-application record
October 6 Evidence Packet · Sept. 30 update
DCAP working packet with explicit unresolved questions and source index
Open PDFDCAP working packet with explicit unresolved questions and source index
What these records do not establish: a final operator/end user, final full-build electrical load, final water demand, final noise, a Project Silo incentive package, or a verified Crusoe-to-Project-Silo connection.
External reporting and official records.
Denver7 · Project Silo proposal
Massive data center proposal in Brighton spurs talk of development moratorium ↗
Massive data center proposal in Brighton spurs talk of development moratorium ↗
City of Brighton · Agenda Center
Official agendas and minutes ↗
Official agendas and minutes ↗
City of Brighton · Long Range Planning
Draft Comprehensive Plan status ↗
Draft Comprehensive Plan status ↗